Dry Dock 5 (P-209) Construction Progress | November 2026
News originally published by
DVIDS - GeorgiaJOINT BASE PEARL HARBOR-HICKAM, Hawaii — The Officer in Charge of Construction Pearl Harbor Naval Shipyard (OICC PHNSY) reports that crews placed more than 600 cubic yards of concrete in November for beams that will support the portal crane rails and foundations for the west electrical substation.
Crews continued to place more than 900 cubic yards of concrete at depths of 40 to 60 feet as part of construction on the main dry dock foundation. They also began installing ballast in the dry dock basin. The added weight will help hold the prefabricated floor units in place once dewatering begins.
Work also began on the water storage tanks for the dry dock’s Fresh Water Fire Pump House. Each completed tank will hold more than 80,000 gallons of usable water.
Legal Disclaimer:
EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.